A bid leveling template is only useful if every bid package gets leveled the same way. Here is the structure that works, whether you build it in a spreadsheet or use a tool.

The structure

  • Rows: one line item per scope element, written from your drawings and specs.
  • Columns: one per bidder, holding their price for each line item.
  • A marker for "not included", so exclusions are visible instead of blank.
  • A total row per bidder, and an adjusted total once gaps are priced.
  • A notes row for qualifications, bid validity, and anything that needs a follow-up call.

Rules that keep it honest

  1. Never leave an excluded item blank. Blank reads as zero, and zero makes a bid look cheaper than it is.
  2. Price every gap. Use the average of the bidders who included it, or your own estimate.
  3. Keep alternates out of the base comparison and compare them separately.
  4. Level the scope before you look at who is lowest, so the headline number does not anchor your judgment.

Handling lump-sum bids

Some subs only give a single number. You can still level them: enter the lump sum as the total, read the inclusions and exclusions carefully, and mark any line items they clearly did not cover. If the gaps are large or unclear, ask for a breakdown before you award. It is a reasonable request on any meaningful package.

Make it repeatable

The same trades come up on job after job, and so do many of the same subs. Saving your line-item structure and bidder list means the next electrical or plumbing package starts half built instead of from a blank sheet.

Level your next bid package in minutes

Free, no account needed. Line up every sub side by side and see exactly who excluded what.

Try the free bid leveler